Use the Work Breakdown Structure, PDM, Scope of Work, and Budget to identify PROJECT RISKS using a risk register showing description, P/I, and responses using the template below.
Risk Register
Scope of Work (SOW)
– Specialized veterinarian and support personnel must be trained and hired for each species.
– Zoo veterinarians must have ACZM certification.
– General grounds crew for maintenance consisting of landscapers and construction crews.
– Guest services group which includes security, ticket sales and special events.
Project Schedule/ Work Break Down Structure
Budget
According to the information in the exercise, The Activity on node is listed below. As Project Manager we must continue keeping the project ahead of schedule and under budget.
The Expected time of the project is 150 days. The critical path of the project contains all activities with slack equal to zero. Then, the critical path is Task 1.01- Task 1.02- Task 1.04 – Task 1.05 – Task 1.06 – Task 1.07 – Task 1.10.
BAC = 121,000
AC = 6,250
PV = 5,045.70
EV = 24,200
SV = 19,154.30; the project is ahead of schedule.
CV = 17,950; the project is under budget.
SPI = 4.7962; the project is ahead of schedule.
CPI = 3.872; the project is under budget.
BAC = 15,000 + 7,500 + 30,000 + 15,000 + 500 + 50,000 + 3,000
BAC = 121,000
AC = 6,250
PV = (% expected work completed) x BAC
The rate per hour of the Wildlife Architect is: 125
The Wildlife Architect was paid: 6,250
DIAGRAM METHOD (PDM)
Identifying Project Risks Using A Risk Register